RENCANA
ANGGARAN BIAYA (RAB)
PEMBANGUNAN
MUSHOLLA “AL-IKHLAS”
NO
|
KETERANGAN
|
Vol
|
Sat
|
Har Sat
|
TOTAL
|
1
|
PEKERJAAN PENDAHULUAN
|
||||
1
|
Pembersihan Lokasi
|
1
|
ls
|
200,000
|
200,000
|
2
|
Bowplank
|
1
|
ls
|
100,000
|
100,000
|
3
|
Pemasangan Listrik 450 watt
|
1
|
ls
|
1,500,000
|
1,500,000
|
4
|
Sumur + Pompa Air
|
1
|
ls
|
4,500,000
|
4,500,000
|
5
|
Air Kerja
|
1
|
ls
|
150,000
|
150,000
|
6
|
Listrik Kerja
|
1
|
ls
|
150,000
|
150,000
|
Sub. Total
|
6,600,000
|
||||
2
|
PEKERJAAN GALIAN TANAH
|
||||
1
|
Galian Tanah Pondasi Tiolet
|
4
|
m3
|
40,000
|
160,000
|
2
|
Galian Tanah Tapak Pondasi musholla
|
8
|
m3
|
40,000
|
320,000
|
3
|
Galian Septictank
|
4
|
m3
|
120,000
|
480,000
|
4
|
Galian Sanitasi
|
24
|
m2
|
10,000
|
240,000
|
Sub. Total
|
1,200,000
|
||||
3
|
PEKERJAAN BANGUNAN
MUSHOLLA
|
||||
1
|
Pondasi Batu Kali
|
8
|
m3
|
120,000
|
960,000
|
2
|
Pondasi Bata
|
4000
|
buah
|
550
|
2,200,000
|
3
|
Batako
|
1200
|
buah
|
2,000
|
2,400,000
|
4
|
Tanah Uruk
|
8
|
m3
|
90,000
|
720,000
|
5
|
Bambu
|
60
|
btg
|
15,000
|
900,000
|
6
|
Balok 8 x 12 (4 m)
|
12
|
btg
|
160,000
|
1,920,000
|
7
|
Balok 6x 12 (4 m)
|
12
|
btg
|
120,000
|
1,440,000
|
8
|
Kaso 4 x 6 (4 m)
|
50
|
btg
|
30,000
|
1,500,000
|
9
|
Reng 2 x 3 (4 m)
|
100
|
btg
|
6,000
|
600,000
|
10
|
Balok 12 x 12 (4 m)
|
2
|
btg
|
200,000
|
400,000
|
11
|
Besi 6 mm
|
30
|
btg
|
15,000
|
450,000
|
12
|
Besi 8 mm
|
20
|
btg
|
35,000
|
700,000
|
13
|
Besi 10 mm
|
12
|
btg
|
53,000
|
636,000
|
14
|
Kawat Bendrat
|
6
|
kg
|
10,000
|
60,000
|
15
|
Paku 7
|
5
|
kg
|
15,000
|
75,000
|
16
|
Paku 5
|
5
|
kg
|
15,000
|
75,000
|
17
|
Paku 10
|
5
|
kg
|
15,000
|
75,000
|
18
|
Paku 12
|
2
|
kg
|
15,000
|
30,000
|
19
|
Amplas
|
12
|
m
|
10,000
|
120,000
|
20
|
Cat Tembok
|
2
|
klg
|
125,000
|
250,000
|
21
|
Balok Plafon Baja Ringan
|
24
|
btg
|
27,000
|
648,000
|
22
|
Kasebot
|
12
|
lbr
|
65,000
|
780,000
|
23
|
Gipsum
|
25
|
buah
|
20,000
|
500,000
|
24
|
Plamir
|
40
|
kg
|
15,000
|
600,000
|
25
|
Cat Plafon (Putih)
|
1
|
klg
|
125,000
|
125,000
|
26
|
Rist Plang
|
24
|
btg
|
50,000
|
1,200,000
|
27
|
Keramik
|
36
|
m2
|
60,000
|
2,160,000
|
28
|
Ramin
|
50
|
btg
|
60,000
|
3,000,000
|
29
|
Pintu
|
2
|
buah
|
800,000
|
1,600,000
|
30
|
Cendela
|
4
|
buah
|
160,000
|
640,000
|
31
|
Ventilasi Loster
|
6
|
buah
|
20,000
|
120,000
|
32
|
Glass Box
|
8
|
buah
|
20,000
|
160,000
|
33
|
Genteng PRES
|
1000
|
buah
|
1,300
|
1,300,000
|
34
|
Nock MANTILI
|
70
|
buah
|
3,500
|
245,000
|
35
|
Cat Genteng
|
2
|
klg
|
120,000
|
240,000
|
36
|
Kubah
|
1
|
buah
|
2,000,000
|
2,000,000
|
37
|
Pasir
|
12
|
m3
|
200,000
|
2,400,000
|
38
|
Koral
|
3
|
m3
|
200,000
|
600,000
|
39
|
Semen
|
80
|
sak
|
57,000
|
4,560,000
|
40
|
Upah Kerja
|
1
|
7,000,000
|
7,000,000
|
|
41
|
Instalasi Listrik
|
1
|
600,000
|
600,000
|
|
Sub. Total
|
45,989,000
|
||||
4
|
PEKERJAAN BANGUNAN TOILET
DAN TEMPAT WUDHU
|
||||
1
|
Batu Bata
|
1500
|
buah
|
550
|
825,000
|
2
|
Pasir
|
4
|
m3
|
200,000
|
800,000
|
3
|
Koral
|
1
|
m3
|
200,000
|
200,000
|
4
|
Tanah Uruk
|
2
|
m3
|
90,000
|
180,000
|
5
|
Semen
|
20
|
sak
|
57,000
|
1,140,000
|
6
|
Besi 6 mm
|
8
|
btng
|
15,000
|
120,000
|
7
|
Besi 8 mm
|
15
|
btng
|
35,000
|
525,000
|
8
|
Besi 10 mm
|
8
|
btng
|
53,000
|
424,000
|
9
|
Bendrat
|
2
|
kg
|
10,000
|
20,000
|
10
|
Pintu WC
|
1
|
lbr
|
250,000
|
250,000
|
11
|
Tandon (500 liter)
|
1
|
buah
|
800,000
|
800,000
|
12
|
Toilet Jongkok
|
1
|
buah
|
150,000
|
150,000
|
13
|
Bak Mandi
|
1
|
buah
|
275,000
|
275,000
|
14
|
Keramik Lantai Dalam (Impresso) 20×20 cm
|
3
|
m2
|
56,000
|
168,000
|
15
|
Keramik Tembok Dalam (Impresso) 20×25 cm
|
16
|
m2
|
56,000
|
896,000
|
16
|
Keramik Lantai Luar (KIA) 20×20 cm
|
6
|
m2
|
56,000
|
336,000
|
17
|
Glass Box
|
2
|
buah
|
20,000
|
40,000
|
18
|
Loster
|
1
|
buah
|
20,000
|
20,000
|
19
|
Cat Tembok Putih
|
1
|
Klg
|
125,000
|
125,000
|
20
|
Kran
|
3
|
buah
|
20,000
|
60,000
|
21
|
Stop Kran
|
1
|
buah
|
35,000
|
35,000
|
22
|
Pipa 1/2 inch
|
2
|
btng
|
20,000
|
40,000
|
23
|
Pipa Paralon 3/4 inch
|
4
|
btng
|
24,000
|
96,000
|
24
|
Pipa 4 inch
|
2
|
btg
|
90,000
|
180,000
|
25
|
Pipa 2 1/2 inch
|
2
|
btg
|
60,000
|
120,000
|
26
|
Sock Drat
|
8
|
buah
|
6,000
|
48,000
|
27
|
Keni
|
12
|
buah
|
4,000
|
48,000
|
28
|
Seal Tape
|
2
|
roll
|
10,000
|
20,000
|
29
|
Lem PVC
|
1
|
buah
|
15,000
|
15,000
|
30
|
Upah Kerja
|
1
|
2,240,000
|
2,240,000
|
|
31
|
Instalasi Listrik
|
1
|
200,000
|
200,000
|
|
32
|
Otomatis Tower Air
|
1
|
150,000
|
150,000
|
|
Sub. Total
|
10,546,000
|
||||
5
|
LAIN-LAIN
|
2,500,000
|
|||
Grand Total
|
66,835,000
|